Fair Isle panorama from Buness
FAIR ISLE

Thursday March 18, 2010

Home
Up
 
 

Fair Isle Renewed
W. M.
Somerville M.Sc.
Newcastle upon Tyne

INSTALLATION AND OPERATION
 

The Fair Isle people have their own myths about island life, which include the mysterious Trows who live in the caves around the cliffs and go about the island, unseen, making mischief for honest folk. We must have flushed out a whole tribe!

 

It started the moment the first shipment arrived at the island harbour. The ship's crane refused to lift the blades in their protective crate and the blades had to be taken ashore individually. The process of moving the unprotected blades to site was nerve wracking but uneventful, and the assembly of the turbine in the prone position was accomplished without major snags. The lift was started and was not going well. After raising the nacelle some three metres it was clear that there was a problem with the wire rope puller, although it was working well inside its rated capacity. The nacelle had to be lowered again onto a ground support. A quick trip to Shetland produced a secondhand wire rope puller of the same capacity, which, after stopping off the tackle, was placed on the wire in tandem with the new puller. This rig allowed us to erect the turbine safely, and avoided the need to dismantle and store the sub assemblies.

 

Commissioning of the turbine against its dump load; always exciting with stand alone machines, went smoothly, and the temporary tie into the system was hooked up. Operation in light winds was satisfactory, but, as the wind strengthened, more load automatically came on on the south heating cable, which was being used to feed the turbine output to the original control panel. This produced a volt drop in the cable, and when wind power was also fed to the service network there was an irritating flicker on incandescent lamps. It was then noticed that, at fairly high power outputs, the turbine was "shivering". This effect was tracked down to flexing of the generator feet, which caused a slight side to side rocking motion. This in turn was varying the belt tension, and modulating the rotational speed of the generator very slightly. The load control units are sensitive to frequency (speed) and were responding to, and maintaining, this disturbance vigorously. A temporary brace to resist the rocking motion alleviated the problem whilst an engineered solution was prepared. This modification reduced, but did not eliminate, the flicker effect.

 

The blade settings and speed of rotation had been arrived at, in full discussion with the blade manufacturers, to give good self-starting and stall at l00kW. After the initial stiffness wore off we got good starting, but found that stall was close to l40kW. This is where a belt drive link can save the day, and we had a step change wheel in hand which brought the speed - down to give stall at 120kW

 

The old machine was lowered and dismantled. The generator and main gearbox were removed and returned to the factory for a full overhaul, including new bearings and shaft seals. The top section of the tower went to Shetland for detail modification of the top flange. We returned to the factory to progress the rebuilding of the nacelle for the 60kW turbine and the remaining control panels.

 

The compressed air supply in the turbine nacelle is only used to release the mechanical brake on a `start' command. Thus, if the air system is leak proof, the compressor motor is only called upon to recharge the receiver after four `starts', and takes about 3 minutes to do so. In practice it is difficult to make the system totally leak free, and the compressor will, typically, run once or twice each day. At the end of a charging run, or when the motor supply is interrupted, the delivery line from the compressor to the receiver is vented, as the motor can not start against pressure. We had considered the possibility that a changeover of supply would be long enough for the motor to stop, though not long enough to vent the delivery line, but, after all, the possibility of a compressor run coinciding with a changeover was remote. We overlooked the fact that a compressor run is likely to follow a start command, and did not anticipate that the turbine could start, take load and initiate a changeover within the compressor run time. After a number of thermal trips, following compressor stall, the compressor failed. A timed disconnect circuit was added to automatically hold off the compressor supply for 20 seconds after any supply interrupt, however brief.

 

On the 3rd of March 1997 at 05.48 the turbine suffered a serious failure of the rotor hub flange on the wind shaft, which resulted in the blade set being damaged beyond repair. All work on the refurbishment of the original turbine was put on hold to await the recovery of the broken shaft and a detailed analysis of the fracture. The design of the shaft and flange had been the subject of a finite element analysis of working stresses to determine its fatigue life, and had been found satisfactory. This analysis was redone with more recent software and higher loadings.  The fatigue life predicted exceeded 30 years. The author's view is that the failure must have been due to a defect in either material or process, but, as the hub had spun on the fracture for at least several revolutions, the evidence of cause, if any, had been destroyed. As a precaution, the shaft flange detail design was revisited and all stress raisers eliminated or reduced. We also added 100% inspection during manufacture by our sub-contractor. As a further precaution, the wind shaft brake disc and the rotor hub were returned to the factory to check for fractures or distortion. These were, rather surprisingly, undamaged. The tower, which had taken direct strikes from all three blades, had some bent bracing bars. These were successfully straightened with purpose-made tools on site. No weld fractures or cracks were found on the tower. Up to the instant of failure the turbine had generated power for 713 hours producing 53,966 kWh an average output of 75.7 kW.

 

The new shaft and the hub and brake disc for the l00kW turbine were shipped to the island and the nacelle rebuilt and assembled to the tower to free the special trailer. The new nacelle assembly and blades sets for both turbines were shipped with the control panels shortly afterwards. The 1OOkW turbine was' bladed and erected first, with the wire rope puller now working properly. The erection tackle was moved to the old site and assembly proceeded well until we found a problem pitching the blades. A short delay followed, to get the hub bolt holes slotted two degrees on Shetland, and assembly was completed without further difficulty.

 

The 60kW turbine was connected up to its turbine control panel and dump load, and was commissioned without any problems. However, it was not stalling until close to 1IOkW output. A change of belt wheels reduced the speed and brought the stall point down to 85kW. This was within the rating of gearbox and generator, but uncomfortably close to the 90kW rating of the dump load. Additional load was added by putting a 3kW water heater in parallel with each of the last five sections of the dump load. These five immersion heaters were mounted in a 30 gallon tank in the diesel house, complete with overheat thermostat and float switch. These last sections of dump will not be powered except when the turbine is running off the system.

 

The changes to the network, and cabling to the network control panel, were planned to minimise outages on the service distribution, and for three days this supply was provided directly from the diesels via a jumper cable. After the network panel had been checked out, including the connections driving the mimic diagram, the diesel and service cables were completed to the network control panel, and we were now able to commission the complete system.

 

The testing of the first three plant options, diesels only, diesels plus 60kW turbine and diesels plus 100kW turbine, went reasonably well. It was noticed that there was still some light flicker present running on the 100kW turbine as sole supply, even though the generator vibration problem was fixed. A clue was given that this tended to be more marked at specific frequencies, suggesting that the controlled domestic load frequencies had become bunched. This was checked and found to be the case. A new programme was worked out for each section of the heating distribution network, to balance the phase loadings and provide a smoother growth of load with frequency. Such programmes can not be perfect, but this exercise did improve the running of the turbine and reduced the flicker until it was barely noticeable.

 

We did succeed in soft coupling the turbines one at a time to the diesel. The 100kW turbine very quickly pulled the diesel up to overspeed, as it is nearly four times more powerful. The 60kW turbine was tested in a steady light wind with about 15kW of capture, and ran coupled for some time. However, it too pulled up and overspeeded the diesel after a slight increase in wind speed. Clearly this form of coupling will only work if the stall power of the turbine is less than the load on the diesel, or if the diesel governor is such that it will permit a limited degree of overspeed without tripping the engine.

 

Operating with diesel and both turbines was much more exciting to commission, and' as it was winter time, work went on after dark. The most perplexing problems were those which only occurred at certain wind speeds or wind directions, and in specific modes of operation. For example, running uncoupled, out of guarantee, in marginal winds, the lead wind turbine would overload, slow down and drop the service load. The lights would go out, the control system would recognise the second turbine was up and running to heating and promoted it to lead turbine. The proving period ran and the service was reconnected and the lights came on. The two minute wait seemed interminable! The logic was changed to allow each turbine to prove it was ready beforehand and wait. This allowed a fast changeover and service was restored in less than one second. This worked well, but inside guaranteed hours of supply the diesel had been told to start, and by the time it was up to speed its load had been taken and the engine then timed out and stopped. To prevent this, a different and longer set up time was introduced when in guarantee time. Most of the problems were resolved by adjusting timing and set levels to obtain a satisfactory service from the system. Some interlocks were added, for example to inhibit coupling when either turbine power went negative. This particular change reduced the outage time when the lead turbine failed service on power loss.

 

The final stage of commissioning, with the synchronisation of the turbines, was anticipated to be difficult. Both wind turbines have brushless alternators as generating plant, and each is equipped with quadrature droop compensated automatic voltage regulators to aid parallel operation. The normal set up procedures, of running at constant speed and switching load on and off, were out of the question with this system. We resorted to setting voltage exactly as required, when each turbine was running steadily between 60% and 75% rated power. The system neutrals, as mentioned earlier, are bonded. When enabled, the synchronising circuit monitors the voltage between the matching phases of the two busbars. The closing circuit is armed at voltage opposition (maximum voltage) and subject to a timer, which sets the maximum slip at 6 cycles per minute. Provided this time has elapsed, the synchronising contactor is closed when the voltage difference falls below the set minimum (30 - 50 volts). We expected that this rather crude method would result in a noticeable surge on synchronising. When it operated the first time we saw nothing, so it was tried again and again and at different settings. This resulted in little or no effect until either the minimum voltage was raised or the time delay shortened significantly.

 

The stability of the system is much improved in synchronised operation, and a little more by closing the two distribution networks into a parallel arrangement when synchronised: We had one more modification to make after these tests. When one turbine is tripped or given a stop command when synchronised, that turbine applies full dump load to brake. Both turbines will feed into the dump load and shed some of the heating load to compensate. Since both are producing power, the negative power trip does not operate and the mechanical brake of the "stopped" turbine has to retard both turbines to the under-frequency cut off. Both induction coupling and synchronising were interlocked to be inhibited by the de-energisation of the "run" relay on either turbine. It is difficult to give a full picture of the system in the scope of this paper, but it is hoped that what is here will be interesting. The system manual has fifty pages of text on just the network control panel.

 


Text and photographs 2008 Dave Wheeler except where otherwise credited. (Logo picture courtesy of Sumburgh SAR)
If you would like to use photographs from this site please contact dave.wheeler@fairisle.org.uk
Further images of Fair Isle are available.  Photographic commissions undertaken, websites authored. 
With over
40,000 visitors to the website each month why not advertise your Fair Isle product or service here?