Dave Wheeler Photography

Dave Wheeler Photography

 


 

 

 


In reality virtually unforgettable!

Wednesday January 23, 2008

 

 

Home
Up
 
 

Fair Isle Renewed
W. M.
Somerville M.Sc.
Newcastle upon Tyne


THE NEW SUPPLY SCHEME
 

The site selected for the 100 kW turbine is one kilometer to the east of the first turbine site, and slightly beyond the eastern boundary of the distribution system. The site is at the summit of a relatively smoothly rounded hill, with open aspects to the prevailing south westerly winds. It is much further from the high cliffs on the, western shore which affect the first site, but it does have cliffs and steep slopes nearby on the eastern shore. The wind speed monitoring that had been carried out suggested that it was a better site, with smoother winds, than the first site. The approach to the site from the nearest hard road was more gradual, and negotiable by tractors over dry turf.

 

A new dwelling and workshop had been built, and another dwelling restored, near to the new site, and a new 95 sq.mm aluminium cable laid to provide additional service capacity from the diesel house at the same time. In anticipation of the new system, this cable had been extended to the new wind turbine site and capped. The heating network distribution cable laid in 1982 was also a 95 sq.mm aluminium cable and ran to Busta, the nearest dwelling some 210m from the site. A control room and store was built by extending a local single storey outbuilding at Busta. The existence in place of these cables, plus a twenty pair telephone cable, also laid in the anticipation of the new scheme alongside the new service cable, allowed us to arrive at a new supply `scheme shown in Fig.2. This scheme is clearly more complex than the original, but a little study will show that it still embodies the features of the original scheme but with more operating options.

 

The diesel generating plant may feed the service distribution network in isolation, provided contactors E and J are not energised. The service network is split into two main sections, those to the north and those to the south of the generator house. There is some further sub-division of the service network, not shown, which energises the various cables in a timed sequence, to load the diesels progressively at start-up. When the service is provided by diesel, each wind turbine may provide power to its portion of the heating distribution network, which is also divided into two. The 60 kW turbine feeds the north heating cables and the 100 kW turbine feeds the south heating cables.

 

Since both wind turbines are each equipped to operate as the only generator on the system, it follows that either may, when the other is not generating, first feed both sections of the heating network and then, if the diesels are shut down (out of guaranteed hours of service supply), and there is sufficient power from that turbine, the supply from the turbine may be allowed to feed the service network also. In considering the logic required for automatic control of the networks, it became clear that this was a very complex problem and there were high risks of uncontrolled coupling, from a sequence interlock failure, and attendant fault damage to plant. A simplifying strategy was needed.

 

Simplification, to a degree, was obtained by using relays to identify the first turbine to signal that it was able to deliver power. This turbine then became the lead turbine and,: as such, was the only turbine allowed to power the service network. The second turbine to come on line was locked out from connection to the service cables. Once a turbine has been selected to lead, it retains this status until it is failed by loading beyond its current capability. This is detected by an under-frequency relay: The second turbine serving part of the heating load will be at, or above, nominal frequency when the lead turbine is failed, and the lead turbine status will be automatically transferred to it. Once more, if there is sufficient power, the service network may be energised, but this time from the new lead turbine;

 

This method of using the power from the turbines was relatively simple, and the loads to the north were in proportion to the 60 kW turbine when compared with the loads in the south on the 100 kW turbine. However, when the lead turbine was also supplying the service power, it could only provide a reduced output to its area of the heating network. It was thus obvious that a way was needed to couple the two turbines so that the distribution of the generated power could be more fairly distributed. There were two basic methods of doing this with simple rugged equipment, and several more complex and more costly methods.

 

The first was to couple the second turbine to the lead turbine using an induction coupler, which consisted of two identical induction motors with their shafts coupled together. With the appropriate phase rotation applied to the windings, the motor connected to the faster second turbine will act as a motor, and the motor connected to the slower, more heavily loaded lead turbine will act as an induction generator. The shafts will be constrained to run at a speed corresponding to the mean of the two frequencies, and the power transferred from the higher frequency supply to the lower will be proportional to the "slip" or half the difference between the frequencies.

 

The second method was to arrive at a method of synchronising the two turbines. These machines are of the fixed pitch, stall regulated type, and have no means of control which will regulate the energy capture to control the speed. Speed is governed by matching the connected heating network load to balance the energy captured by the turbine.  There is no simple way of remotely adjusting the settings of the distributed load controllers which regulate the switching of the domestic heating units. These are the governing loads in control when the turbine is operating on the network. One possibility was to modify the dump load controller to allow the set frequencies to be varied on command. This, on reflection, was not considered wise in view of the need to keep close matching of the dump load profiles, as discussed earlier, and because of the dual safety functions of ultimate speed governor and fast acting electrodynamic overspeed brake.

 

Coupling techniques, using power electronics to transfer power between the wind turbine busbars, were considered briefly but thought to be vulnerable to damage by the numerous switching operations on the system in service.

 

The final choice for synchronising used a phase matching technique, subject to a limit on differential speed, operating in conjunction with an induction coupler. This choice had the added attraction that, should the synchronising method fail, we had the fall back position of operating induction coupled.

 

The scheme as it is shown in Fig.2 does not remind us that the 100 kW turbine is one kilometer distant from the diesel generator house where the network control panel must be located.

 

Protective multiple earthing is used throughout both distribution networks, and neutrals are bonded to cable armour and local earths at each consumer cut out. In addition, continuous earth tape bonds the first wind turbine foundation earth to the diesel generating plant earth, which is laid in a permanently wet meadow adjacent. The new wind turbine site is on a well-drained hilltop with sparse turf cover, and the local tower earthing tape runs 200m away from the cable lines to the only permanently wet ground in the vicinity. This led to concern about possible damage in the event of a lightning strike on the 100 kW turbine.

 

To reduce the risk of damage to the control system and the telephone cable to the diesel house, by the ground wave following a lightning strike, it was decided to provide galvanic separation, between the 100 kW turbine control system and the telephone link, of up to 2 kV. This precaution increased the complexity of command and control, and set a restriction on the information that could be sent over the telephone cable.

 

The contactors shown as J and K in Fig.2 which connect the 100 kW turbine to the south service cable and the south heating cable respectively are housed, with the associated circuit breakers, in an isolating switch panel mounted beside the turbine control panel in the 100 kW control room at Busta. Coil power is drawn from the turbine but is under the command of signal isolating relays operated over the telephone cable from the network controller in the diesel house.

 


Text and photographs 2008 Dave Wheeler except where otherwise credited. (Logo picture courtesy of Sumburgh SAR)
If you would like to use photographs from this site please contact dave.wheeler@fairisle.org.uk
Further images of Fair Isle are available.  Photographic commissions undertaken, websites authored. 
With over
40,000 visitors to the website each month why not advertise your Fair Isle product or service here?