|
THE WIND TURBINES
The design of the new wind turbine and the
refurbishment of the old turbine draw heavily on the experience of operating
in .the extreme conditions on Fair Isle. The early gearbox failures on the
first machine highlighted the futility of putting a brake on the output
shaft of the gearbox and the risk, fortunately avoided by prompt action, of
a runaway turbine rotor and potential destruction of the entire turbine. The
enforced shut down of the old turbine in 1996 was due to the failure of the
low speed shaft oil seal on the gearbox. Positioned between the windshaft
main bearings, the seals could not be replaced without dismantling the
complete turbine and nacelle.
The design, for all such isolated sites,
must place a high priority on safety, damage limitation factors and ease of
servicing and repair. This philosophy required a completely new nacelle
layout for the old turbine, placing the mechanical brake on the wind shaft
between the main bearings and the gearbox on an overhung portion of the
shaft behind the main bearings. The final drive to the generator is by wedge
belts which, although somewhat less efficient,
will act as a torque
limiter
by slipping if seriously overloaded. These
wedge belts are not expensive and
are easily replaced if worn or
damaged. The mechanical brakes are "fail-safe", applied by springs and
released by compressed air at 7 bar, provided the control
solenoid valve is energised. Thus,
loss of control current or loss of air pressure will automatically apply the
brakes and stop the turbine. However, the loss of air pressure may be slow
and allow the brakes to come on slowly and cause the pads to wear out. To
prevent this, a pressure switch will reset if the line presssure falls below
that needed to fully release the brakes, and this will, in turn, apply the
brakes immediately. The key information on these two, fixed pitch, stall
regulated, turbines is listed below:
|
Wind turbine
Diameter
Blades- LM x 3
Tip pitch - deg.
Speed - r.p.m.
Gearbox - Fenner
Drive ratio O.A.
Generator
Rating - kW
KVA
Yaw drive |
60kW
15.9m
8HMT
+3.25
44
L20
1:32.73
B464B
96
120
Fantail |
100kW
19.1m
9.7HMTB
+3.25
41
M20
1:36.35
UCI274F
132
165
Fantail |
The gearbox
and the generator
from the old turbine were both
inspected and found to be in good condition when the machine was dismantled.
These units were overhauled, fitted with new bearings, and reused in the
60kW nacelle. The tower required minor modification to the top flange and
was also reused.
Safety and damage limitation
considerations led to a number of sensors and switches being installed on
each turbine for the following functions:
-
Rotor
overspeed.
-
Generator overheat.
-
Main gearbox oil level low.
-
Low brake release air pressure.
-
Cable twist exceeds four turns.
-
Drive belts damaged or broken.
-
Brake adjustment required.
-
Compressor running.
-
Nacelle safety lockout switch.
These functions are self-explanatory and
for this site considered essential. Further, the
overspeed
sensors and relays are duplicated, and the
relays set up in a "fail-safe" mode. All these sensors and switches provide
indication to assist the operators, both at the local control pedestal at
the base of the tower and in the turbine control panel in each control room.
A small pony motor was installed in each
nacelle to aid start-up in marginal wind conditions. This, it was hoped,
would reduce the time required to commission each turbine when shaft seals
and belts were new and stiff. It was also thought to be a wise precaution in
the event that the self-starting capability of the blade settings proved to
be underestimated. The compressed air to release the brakes is provided by a
small commercial, single phase compressor, which is mounted on, and
automatically charges, a 25 litre receiver in the nacelle, to 10 bar.
The turbine blades are equipped with
"twist tip" air brakes, centrifugally released on
overspeed
and mechanically linked to trigger at the
same time. For simplicity the manually reset option was selected.
|